Construction Update : 29 Dec 2010

It's end December 2010 now. Owners of Phase 2 in CP2 who were promised delivery in Dec 2010 must be disappointed, this is what their towers look like and here's a panoramic view of what the status look like, click on the picture to see a proper view




Work for towers 23,24,25,26 is just beginning , you can see the excavation being done in Dec 2010 here

We're hearing of plans to move the EWS quarters from where it was shown in the layout to a location in this corner. That would mean it will be right in front of towers 1 to 6.

This is where the EWS quarters were supposed to be, along with the Primary school. The school location is now a generator room :

This was the actual dream 5 year ago, just for reference.


5 comments:

  1. feel totally cheated , RWA should take steps to take STAY ORDERS from the court for stopping builder to make change in Layout Plan and cheat customers .

    ReplyDelete
  2. Hi - You mentioned the start of excavation for towers 23-26. Any idea if this includes tower 22 as well?

    Thanks,
    Aman

    ReplyDelete
  3. No construction has started for towers 19, 20, 21 & 22 at all. Even the excavation isn't done, you can click on the first image on top to see.

    ReplyDelete
  4. I think all builders are cheats in Delhi. How can they show a beautiful picture and destroy the dreams of hundreds of families? How can they use someone else's money to do construction? They should be severely punished for this.

    I suggest we all immediately goto court and get a stay order against the builder charging any more money till the whole project is completed.

    ReplyDelete
  5. Sweta Estates is a unprofessional organisation. I've been conned by their own people and they promised a compensation which was never done. Someone in Sweta estates mentioned that i should go to court and thats the only way things work out here. They're professional cheats.

    ReplyDelete